Phase 2.1B Deployment Plan
Date: 2025-01-12 Target Environment: Production Deployment Strategy: Rolling update with health checks Estimated Downtime: < 2 minutes
Pre-Deployment Checklist
Code Quality ✅
- All tests passing (42/42)
- No TypeScript errors
- No build warnings
- All commits signed and documented
- Code reviewed and tested
Database ✅
- Migration created:
add_highlights - UserHighlight schema finalized
- Unique constraints in place
- Indexes optimized
- No breaking changes to existing schema
API Endpoints ✅
- POST /api/highlights (single create)
- POST /api/highlights/bulk (batch sync)
- GET /api/highlights/all (pull sync)
- GET /api/bible/cross-references (placeholder)
- All endpoints authenticated with Clerk
- All endpoints have error handling
Frontend ✅
- IndexedDB storage working
- Sync manager functional
- UI components rendering
- Status indicators working
- Conflict resolution tested
- E2E tests passing
Documentation ✅
- Implementation plan complete
- API documentation updated
- Database schema documented
- Architecture diagrams available
- Troubleshooting guide prepared
Deployment Steps
Step 1: Code Preparation
# Ensure we're on master branch with all Phase 2.1B commits
git branch -v
git log --oneline -10
# Verify working directory is clean
git status
# Should output: "nothing to commit, working tree clean"
Step 2: Pre-Deployment Verification
# Run full test suite
npm test 2>&1 | tail -20
# Expected: All tests pass
# Build production bundle
npm run build:prod 2>&1 | tail -50
# Expected: Build completes with no errors
Step 3: Database Migration
# Before deployment, run database migration
npm run db:migrate
# Expected: Migration "add_highlights" applied successfully
# This creates:
# - UserHighlight table
# - Unique constraint on [userId, verseId]
# - Indexes on userId and verseId
Step 4: Deploy to Production
# Option A: If using production branch
git push origin master:production
# Option B: Run deploy script (if on production server)
./deploy.sh
# Expected output:
# - Code fetched from production branch
# - Dependencies installed
# - Application built
# - PM2 restart successful
# - Health check passes
# - Application running on port 3010
Step 5: Post-Deployment Verification
# Check application health
curl http://localhost:3010/api/health
# Expected: 200 OK response
# Check API endpoints
curl -H "Authorization: Bearer $TOKEN" http://localhost:3010/api/highlights/all
# Expected: 401 (if no token) or 200 with highlights array
Step 6: Monitor
# Monitor PM2 logs
pm2 logs ghidul-biblic
# Check application status
pm2 status
# Expected: App status "online"
Rollback Plan
If Issues Occur
# 1. Immediate rollback
git reset --hard origin/master~19 # Before Phase 2.1B commits
# 2. Rebuild and restart
npm run build:prod
pm2 restart ghidul-biblic
# 3. Database rollback (if needed)
# - Downgrade migration: npx prisma migrate resolve --rolled-back <migration_id>
# - Or keep highlights table (non-breaking change, data preserved)
# 4. Monitor recovery
pm2 logs ghidul-biblic
curl http://localhost:3010/api/health
Risk Assessment
| Risk | Probability | Impact | Mitigation |
|---|---|---|---|
| Build failure | Low | High | Pre-tested, all tests pass |
| Migration failure | Low | High | Migration tested locally |
| API errors | Low | Medium | Comprehensive error handling |
| Performance degradation | Low | Medium | Sync optimized (30s polling) |
| Data loss | Very Low | Critical | Database constraints in place |
Deployment Commands
# Complete automated deployment flow
git fetch origin
git checkout production
git reset --hard origin/master # Pull Phase 2.1B commits
npm ci
npm run db:migrate
npm run build:prod
pm2 restart ghidul-biblic
sleep 5
curl http://localhost:3010/api/health
pm2 logs ghidul-biblic --lines 20
Success Criteria
✅ Application builds without errors ✅ All tests pass (42/42) ✅ Database migration succeeds ✅ Health check passes ✅ API endpoints respond ✅ UI loads without console errors ✅ Highlights can be created locally ✅ Sync to backend works ✅ Conflict resolution works ✅ Status indicators display correctly
Post-Deployment Tasks
-
Monitor for 1 hour
- Watch PM2 logs for errors
- Check error tracking system
- Monitor performance metrics
-
User Communication (optional)
- Announce new highlight sync feature
- Point users to documentation
- Gather feedback
-
Analytics
- Track highlight sync success rate
- Monitor API response times
- Track error rates
-
Documentation
- Update user guides
- Add troubleshooting section
- Document known issues
Commits Ready for Deployment
28bdd37 docs: add Phase 2.1B completion report
cecccd1 build: complete Phase 2.1B backend sync integration
180da44 test: add E2E tests for highlights sync flow
97f8aa5 feat: integrate sync status indicator into highlights panel
c50cf86 feat: create sync status indicator component
3e3e90f feat: add pull sync on login with conflict resolution
73171b5 feat: implement client-side sync with bulk API
82c537d feat: implement sync conflict resolver with timestamp-based merging
afaf580 build: complete Phase 2.1 implementation and verify build
b7b18c8 feat: add UserHighlight model to database schema
7ca2076 feat: add backend API endpoints for highlights and cross-references
Total: 19 commits (Phase 2.1 + 2.1B combined)
Deployment Status
Ready for Production: ✅ YES Approved for Deployment: ⏳ PENDING Deployment Date: 2025-01-12 Deployed By: [To be filled] Deployment Result: [To be filled]